2014 Hummels Wharf Office Expansion Construction

October 16, 2014

The exterior brick work is now being installed

 

 

September 29, 2014

Interior sheeting continues and the interior walls are being constructed

 

September 26, 2014

Outside "elevated" look is taking shape

 

September 22, 2014

Work begins on the inside

September 17, 2014

Shingles are now being installed

 

 

September 14, 2014

Sheeting of the roof begins

 

 

September 08, 2014

The roof system is quickly going into place

 

 

September 04, 2014

Walls are basically complete and roof truss system will be lifted into place in the next few days

 

 

August 28, 2014

We now have walls going up

 

August 26, 2014

Concrete floor has been poured

 

 

 

 

August 12, 2014

Footer/foundation and plumbing

 

August 5, 2014

Excavation Begins

 

August 4, 2014

Drive through lanes are re-routed around the construction site